Score Top Marks With Our MEM234026A Develop and Coordinate Engineering - Related Contingency Plans Assignment Help!

Home   Course  
Previous << || >> Next

MEM80112 - Graduate Diploma of Engineering

MEM234026A Develop and Coordinate Engineering - Related Contingency Plans

ECA Graduate Institute, Australia

DON'T MISS YOUR CHANCE TO EXCEL IN ENGINEERING ASSIGNMENT! HIRE TUTOR OF EXPERTSMINDS.COM FOR PERFECTLY WRITTEN MEM234026A DEVELOP AND COORDINATE ENGINEERING - RELATED CONTINGENCY PLANS ASSIGNMENT SOLUTIONS!

Contingency planning: The organization for which a contingency plan has to be developed is into manufacturing field and is named Draslovka Chemical Plants present in Kolin (UNECE, 2018). It has a manufacturing plant that produces hydrogen cyanide and other caustic products. However, contingencies can be needed quite frequently since there can be sudden risk in the equipment or lack of availability of essential human resources.

1. Establish contingency plan task

a. Review existing technologies, processes, standards

Answer: Review existing technologies: At the moment, the firm does not make use of expensive or fancy technologies to cope with the risks. Occupational health and safety standards are already in place as people present in the manufacturing plant need to ensure safety while at work and understand the available processes to reach out whenever there is an emergency. There is also accident prevention act.

There are 3 technologies primarily in use inside the firm - biometric attendance system, plant to convert the raw material into finished product and quality assessor. The works are allocated for the day based on the attendance percentage of the resources for that day. This appears weak as there is no backup plan and when there is a need for an expert to assess quality, it is left as such. Therefore, there can be a schedule overlap/delay.

The present standards and processes do not have essential backup plans to address risks or sudden deviations in the events.

b. Clarify contingency plan objectives and scope with client

Answer: There are 3 objectives for the contingency plan.

- Reduce risk of disasters

- Improve preparedness of the organization to a natural catastrophe

- Predict the financial and operational requirements for a specific accident

c. Prepare task schedules and requirements for development

Answer: 

Task detail

Schedule

Requirement

Past accident assessment

3 weeks

Reach out to employees who have been working since decades and list out the accidents faced by them

Study of existing technologies and standards

2 weeks

Meet supervisors of different facilities to note down

Advise plans for each risk situation identified

4 weeks

Brainstorm the accidents that can happen and develop plans to deal with them effectively

d. Establish contingency planning team, if required, and assign

Answer: Contingency planning team: There are 3 roles that constitute contingency planning team for the chosen firm (TRP, 2011).

Roles

Responsibilities

Team leader

First person to respond to the disaster and decides the suitable recover process

Administrator

Brings together the stakeholders for specific incidents, administers the available resources at any specific minute, takes the responsibility to record minutes of meeting

Coordinator

Travels with the team leader and the team members/victims and improves the usefulness of effort taken by the team leader in the recover process. Also, coordinator is responsible to facilitate communication across different levels of management.

2. Conduct impact assessment

a. Prepare comprehensive list of potential incidents

Answer: List of potential incidents: The firm has already faced over 3 major industrial accidents as of 2006 and there is a high probability for similar incidents to occur.

Here is a list of potential incidents (NTU, 2015):

- Exposure of resources to chemicals

- Lack of understanding on how to use a specific equipment

- A part of the manufacturing plant is not working and the process hampers all of a sudden

- Wrong choice of chemicals to produce a substance

- Poor inventory management/ underutilization

b. Rate each potential incident for impact severity level

Answer: 

Potential incident

Likelihood

Impact

Exposure of resources to chemicals

 

High

High

Lack of understanding on how to use a specific equipment

Medium

High

A part of the manufacturing plant is not working and the process hampers all of a sudden

Low

Medium

Wrong choice of chemicals to produce a substance

Low

High

Poor inventory management/ underutilization

Medium

Medium

c. Identify which incidents will be included in plan

Answer: Incidents to be included in plan: There are 2 incidents to be included in the plan:

- Exposure of resources to chemicals

- Lack of understanding on how to use a specific equipment

The reason to choose these two incidents is because they revolve around a common problem - human resource(NTU, 2015). When the human resources working in the manufacturing plant are not properly trained, there are possibilities for wrong combinations or exposure to chemicals. Since the company is already producing poisonous products, the incident in reality can cause fatal accidents to the resources.

This has to be taken seriously and the degree of safety has to improve further so employees are protected at all times.

SAVE YOUR HIGHER GRADE WITH ACQUIRING MEM234026A DEVELOP AND COORDINATE ENGINEERING - RELATED CONTINGENCY PLANS ASSIGNMENT HELP AND QUALITY HOMEWORK WRITING SERVICES OF EXPERTSMINDS.COM!

3. Develop contingency plan

a. Formulate an action plan to deal with each significant risk

Answer: Action plan for each risk

Risk nature

Action plan

Exposure to chemicals

Identify resources that directly use chemicals and ask them questions to test their understanding.

Schedule a training session for questions that were unanswered.

Expose the trained resources to manufacturing facility to assess how they respond to accidents.

No knowledge about equipment

Identify resources that are using specific equipment.

Ask supervisor to train them about usage of equipment.

Chemical attack

Categorize chemicals present inside the facility based on the severity of impacts. For instance, the most poisonous one can be marked with a suitable danger symbol and people can just learn the symbols and carefully use them.

Stick posters around the manufacturing plant for the resources to know the deadly combinations that should be avoided.

Unavailability of employees

Create a register of employees who can be used for 2 departments and can be adjusted as backup.

Train them together.

b. Ensure occupational health and safety (OHS) requirements, and other regulatory requirements and enterprise procedures

Answer: Occupational health and safety (OHS) requirements: There are 3 OHS legislative procedures that need to be implemented by this firm. 

- Approved codes of practice

- Occupational health, safety and welfare act

- Toxic substance

At this instance, it is important to cover the occupational illness and involve workplace safety and insurance board to address the affected employee inside the workplace.

c. Determine resources required to support plans

Answer: Resources needed to support plans: There are a number of resources to support the action plans mentioned above.

- External resource who can educate the employees about chemicals and add information about deadly chemicals

- Supervisor who can quote the human resource need for a facility of the manufacturing plant to run efficiently each day

- Educational materials in multimedia format for the employees to quickly understand how equipment works (WHO, 1999)

- Employee attendance system (technology) to keep note of the employees present in a day and arrange backup accordingly

d. Assign responsibility for each planned action

Answer:

Planned action

Responsibility

Training resources

Establish strategy to involve human resources in this plan.

Coordinate both the ends.

Assess the compliance levels.

Categorizing chemicals

Take the help of supervisor.

Categorize the chemicals based on the severity/poisonous nature.

Allocate a person who can ensure that they are not misplaced at the end of the day.

Employee attendance system

Make note of the attendance rate for a particular day

Train employees to use it without fail

Train supervisor to use round robin structure to allocate employees for the facility

e. Determine costs associated in planned responses

Answer: Costs associated in planned responses: Training resources can cost about $70 per resource. Categorizing chemicals can cost less than $500 on the whole.

Employee attendance system can cost about $3000 right from implementation till training of the employees to get acquainted to the system.

f. Determine trigger points for planned responses

Answer: - Human error during categorization of chemicals: - Too many absentees on a specific day that even the backup resources are unavailable (Bitsch et al, 2003)

- Training has not reached the desired audience and the employee continues to mix the chemicals.

- Supervisor absent on a specific day that people have not got instructions

- Cost exceeds the proposed number

g. Review plan proposals and costs with client and stakeholders to required

Answer: Plan proposal and cost reviews: The plans mentioned so far are certainly helpful to mitigate the probability of accidents. Since the company has already faced a couple of them due to poor knowledge of employees and due to insufficient training and technology systems, the plans along with their costs definitely seem to be worthy. The only concern now is to work on sudden cost overheads during the implementation of the plan. 

The cost will have to be adjusted accordingly so we are prepared for overheads.

ORDER NEW MEM234026A DEVELOP AND COORDINATE ENGINEERING - RELATED CONTINGENCY PLANS ASSIGNMENT AND GET 100% ORIGINAL SOLUTION AND QUALITY WRITTEN CONTENTS IN WELL FORMATS AND PROPER REFERENCING!

4. Implement and maintain the plan

a. Finalise planning, including ensuring preparation of all required instructions.

Answer: Finalize planning with drawing and specifications: The plan to implement the actions above is as follows:

- Begin with the training of first 50 resources who have been performing well and can take the responsibility to inform their peers about it

- Assess the accuracy

- Implement the attendance system to one of the facilities with the lowest number of people to determine change resistance. Extend it in due course of time to other facilities.

Communicate plan with all personnel

The first step is to arrange a brainstorming session by including all the 3 roles to sit together and list down the resources to be included for training.

The second step is to let the coordinator to arrange the first batch of the resources and let supervisor intervene and reflect on the changes. This can help understand if he/she is interested and the need for external trainers.

The next step is to reach out to the top management to conduct the training for the entire facility on single day.

Standard procedures to ensure plan is maintained

- Enter in the log sheet if the plan is followed for the day

- Have employee feedback session weekly where the employees reflect their concerns

NEVER BE CAUGHT IN PLAGIARISM, AVAIL MEM234026A DEVELOP AND COORDINATE ENGINEERING - RELATED CONTINGENCY PLANS ASSIGNMENT HELP SERVICE OF EXPERTSMINDS.COM AND SAVE HIGHER MARKS!

Get brilliant solutions of assessments and quality ECA Graduate Institute assignment help service for different courses and units, such as:

  • MEM234002A - Integrate engineering technologies Assignment Help
  • MEM234035A - Maintain and apply technical and engineering skills Assignment Help
  • MSMENV672 - Develop workplace policy and procedures for environmental sustainability Assignment Help
  • MEM234001A - Plan and manage engineering-related projects or operations Assignment Help
  • MEM234028A - Produce and manage technical documentation Assignment Help
  • MEM234021A - Apply statistics to technology problems Assignment Help
  • MEM234008A - Design plant using computer simulations Assignment Help
  • MEM234027A - Plan and manage materials supply for an engineering project or manufacturing operation Assignment Help
  • MEM23123A - Evaluate manufacturing processes Assignment Help

Tag This :- EM1989ASH0404OTH MEM234026A Develop and Coordinate Engineering - Related Contingency Plans Assignment Help

get assignment Quote

Assignment Samples

    Criminal Law Assignment Help

    Assignment on the criminal law and then plan about the active in investigating violations of health care laws.The planning needs to be done for handling HC

    Public Health Issue Assignment Help

    public health issue assignment help - Tobacco usage - Public Health Issue Assignment Research and discuss public health issue in the United States today.

Get Academic Excellence with Best Skilled Tutor! Order Assignment Now! Submit Assignment